ZILLION, after the completion and connection of the first three 2MW photovoltaic systems, continues its upward trajectory and consolidates its position in the field of leading EPC contractors.
Within the framework of RAE’s Competitive Procedure No. 4/2018, ZILLION undertook the design, procurement and construction of eight additional photovoltaic systems with a total capacity of 7MW.
- 1 x Photovoltaic system with a power of 1MW, owned by the company Energeiki Imathias IKE, which is located in the Municipal Unit of Koilada, Municipality of Larissa.
- 1 x Photovoltaic system with a power of 1MW, owned by the company Energeiki Imathias IKE, which is located in the Municipal Unit of the 3rd District of Larissa, Municipality of Larissa.
- 1 x Photovoltaic system with a power of 500kW, owned by the company Energeiki Imathias IKE, which is located in the Municipal Unit of Galliko, Municipality of Kilkis.
- 1 x 1MW photovoltaic system, owned by the company Lumen Hellas Energy S.A., located in the Municipal Unit of Giannitsa, Municipality of Pella.
- 1 x 1MW photovoltaic system, owned by the company Lumen Hellas Energy S.A., located in the Municipal Unit of Galliko, Municipality of Kilkis.
- 1 x 1MW photovoltaic system, owned by the company Sunworks Arcadia Energy S.A., located in the Municipal Unit of the 3rd District of Larissa, Municipality of Larissa.
- 1 x 500kW photovoltaic system, owned by Sunworks Arcadia Energy S.A., located in the Terpsithea Municipal Unit, Larissa Municipality.
- 1 x 1MW photovoltaic system, owned by Sunworks Arcadia Energy S.A., located in the Municipal Unit of Kallithea, Municipality of Oreokastro.
The above projects are in the design and procurement stage of basic equipment. The completion of construction and their successful connection to the HEDNO network is expected to take place before December 2019.